THE COST IMPACT OF FRONT END ENGINEERING DESIGN (FEED) ACCURACY FOR LARGE INDUSTRIAL PROJECTS
รหัสดีโอไอ
Title THE COST IMPACT OF FRONT END ENGINEERING DESIGN (FEED) ACCURACY FOR LARGE INDUSTRIAL PROJECTS
Creator Mounir El Asmar, G. Edward Gibson, Jr.
Contributor Mohamed Asem Abdul-Malak, Hiam Khoury, Amarjit Singh, Siamak Yazdani
Publisher ISEC PRESS
Publication Year 2561
Keyword Front end planning, Construction industry institute, Project definition, Rating index, Cost growth, Performance
Abstract Assessing the accuracy of front end engineering design (FEED) for large industrial projects is a critical task with the potential to considerably impact overall project success. At this early phase of the project, the owner's expectation is to be able to make informed decisions including cost predictions to determine whether the project should proceed to the next phase. The primary objective of this paper is to evaluate FEED accuracy and measure its impact on project cost performance. The authors collected and analyzed data from 33 completed large industrial projects representing over $8.83 billions of total installed cost. A primary finding is that projects with high FEED accuracy significantly outperformed projects with low FEED accuracy in terms of cost growth in relation to the approved budget at Phase Gate 3. This finding assists owners and contractors focusing on the front end planning phases of their large industrial projects to considerably improve cost performance.
ISBN 978-0-9960437-5-5
Language English
URL Website https://www.isec-society.org/
Website title ISEC Society
International Struct Eng and Constructn Society

บรรณานุกรม

EndNote

APA

Chicago

MLA

ดิจิตอลไฟล์

Digital File
DOI Smart-Search
สวัสดีค่ะ ยินดีให้บริการสอบถาม และสืบค้นข้อมูลตัวระบุวัตถุดิจิทัล (ดีโอไอ) สำนักการวิจัยแห่งชาติ (วช.) ค่ะ