ON MODELING ACTIVITY CRASHING AND OVERLAPPING: A FIRST ALGORITHM
รหัสดีโอไอ
Title ON MODELING ACTIVITY CRASHING AND OVERLAPPING: A FIRST ALGORITHM
Creator Kamel Elamrousy, Pablo Ballesteros-P้rez
Contributor Mohamed Asem Abdul-Malak, Hiam Khoury, Amarjit Singh, Siamak Yazdani
Publisher ISEC PRESS
Publication Year 2561
Keyword Compression, Acceleration, Delay, Schedule, Stochastic, Productivity, Risk
Abstract Accelerating construction projects is a commonly used method for meeting the project deadlines and/or compensating for current delays. There are several approaches to speedup a project, such as activity crashing and overlapping. Activity crashing means reducing activity durations through adding more resources. Activity overlapping means executing certain activities in parallel when they were supposed to be sequential in the original plan. Construction management literature is mostly focused on studying each acceleration mode separately, while the focal point of this paper is to develop a joint model and a first algorithmic implementation that involves both acceleration methods. Particularly, on reviewing the project management and scheduling literature, a mathematical model combining activity crashing and overlapping is reformulated. Also, a Genetic Algorithm is implemented on a fictitious case study. Preliminary findings of the model and algorithmic implementations identify that activity crashing alone and a mixed approach are preferred when significant compression is required, whereas activity overlapping is recommended for minimizing compression costs when only a small compression is required.
ISBN 978-0-9960437-5-5
Language English
URL Website https://www.isec-society.org/
Website title ISEC Society
International Struct Eng and Constructn Society

บรรณานุกรม

EndNote

APA

Chicago

MLA

ดิจิตอลไฟล์

Digital File
DOI Smart-Search
สวัสดีค่ะ ยินดีให้บริการสอบถาม และสืบค้นข้อมูลตัวระบุวัตถุดิจิทัล (ดีโอไอ) สำนักการวิจัยแห่งชาติ (วช.) ค่ะ